Headbox Maintenance & Overhaul

Horizontal CD basis weight control and jet stability — lip replacement, apron repair, profile zeroing and alignment.

FunctionStock distribution onto the wire
Key partsLip bars / apron / top-lip mechanism
Typical duration8–72 h

1 · Equipment Overview

FunctionDistribute stock evenly across the width; control CD basis weight and fibre orientation.
PrincipleStock passes the distributor and turbulence generator, then jets from the lip opening.
Key adjustmentsLip opening, top-lip horizontal/vertical position, dilution water.
Core precisionLip tip gap 0.20–0.25 mm

2 · Maintenance Process

Incoming inspectionAfter cleaning, visually inspect apron leading edge, lip bars and flow surfaces item by item; magnified check with camera / USB microscope.
Lip opening surveyOpen to 15 mm; measure deflection at every adjusting rod with a dedicated measuring arm and dial gauge; record the profile.
Top-lip mechanism checkBacklash test of horizontal/vertical travel gears (air pad + dial gauge); verify limit switches.
Lip bar replacementTemperature-soak new lip bars 24 h; remove clamp plates, springs and rods, clean threads, apply silicone grease, refit. Clamp bolts 42 N·m; ball-joint lock nut 50 N·m; tip gap 0.20–0.25 mm.
Apron repairStraighten bent zones with dedicated hydraulic tooling; grind the leading edge back to profile; weld-repair deep damage and regrind.
Corrosion repairReplace supports with stainless steel; dry-ice blast corrosion; spot-prime and top-coat.
Flow-surface treatmentGrind and polish flow surfaces; optional low-surface-energy coating to reduce fibre build-up and extend cleaning intervals.
AlignmentRe-verify level and parallelism to the forming roll; adjust top-lip parallelism to the apron.
Lip zeroingZero the dial gauge at every rod; keep adjacent-rod reading difference ≤ 0.2 mm to avoid permanent deformation.
Final verificationRe-measure lip opening profile and tip gap; confirm no grease residue in the lip channel; record and hand over.

3 · Key Process Photos

Headbox interior — lip channel and adjusting mechanism
Headbox interior — lip channel and adjusting mechanism
Top-lip bar close-up with adjusting rods
Top-lip bar close-up with adjusting rods
Lip edge — tip wear and deposit check
Lip edge — tip wear and deposit check
Apron flow surface condition
Apron flow surface condition
Flow surface after regrinding
Flow surface after regrinding
Local bending and rust on apron
Local bending and rust on apron
Apron leading-edge profile check
Apron leading-edge profile check
Roll surface and jet face
Roll surface and jet face
Frame corrosion zones
Frame corrosion zones

4 · Acceptance & Handover

Lip tip gap 0.20–0.25 mm; adjacent-rod deviation ≤ 0.2 mm; apron leading-edge profile restored with flatness within tolerance; frame corrosion removed and coated; alignment and parallelism re-verified; no grease residue in lip channel; measurable improvement in CD basis-weight 2σ.