ScopeShoe press / extended-nip press (long-nip dewatering)
SystemHPU + shoe assembly + lubrication metering manifold
Shutdown & depressurizeStop, depressurize, sample oil; record level and temperature.
Hydraulic unitInspect tank, filter elements, breather; tighten piping joints.
Shoe inspectionCheck shoe / piston assembly, pivot strips, inclined springs.
Seal renewalInspect and replace piston / bronze seals.
Valve verificationCalibrate equalising, proportional and unloading valves; relief valves annually.
Lubrication calibrationCalibrate manifold header pressure. ≈ 100 psi
Oil treatmentBypass filtration / dehydration; top up by grade — never mix brands.
Pressurise & loadBuild nip pressure; staged loading test.
Curve verificationVerify nip pressure curve against load setpoints.
Trial runCheck internal / external leakage, oil temperature and flow.
Nip loading stable at setpoint; no internal/external leakage; oil temperature and level normal; high-pressure flow in range; nip pressure curve within tolerance; manifold lubrication pressure to target.